Delivery & Installation
The delivery, installation, and verification of the Aquicore infrastructure is taking place.
Scope Project
Aquicore will confirm hardware and integrations required to complete the installation. The building team will complete the site survey of infrastructure that will be connected to, providing power source options and communication protocols. They will also ensure a quality cellular signal for AQ Hub placement.Deliver Hardware
Hardware will be delivered to either the on site team, or the contractor being used to perform the installation. Confirm hardware has arrived with the Project Engineer assigned to your order.Install Hardware
Work with electrical/mechanical contractor to install hardware in the specified locations in your building.Connect to KYZ pulse output/Modbus RTU terminals
Connect the meters included in the Scope of work to the Aquicore equipment using the correct communication protocol terminals on the Aquicore circuit board. Ensure that the Aquicore devices are online and can report data to the Aquicore Platform.First Meter Reading
Perform the first manual meter kWh/gallon/BTU meter reading. A timestamped reading of the meter faceplate will suffice.Second Meter Reading
Perform the second manual meter kWh/gallon/BTU meter reading. A timestamped reading of the meter faceplate will suffice. The manual readings will be compared to the raw data entering the Aquicore Platform from the same meter in order to commission or validate the meter.Confirm All Meters Online & Commissioned
Make sure that all meters that were connected to and/or installed have commissioned in the Aquicore Platform. Once this is completed, the delivery process has been completed.